After 2030

Planned activities include decommissioning, dismantlement and removal of the spent fuel canister area, the reactor and reactor building....

2024 – 2030

Planned activities include the reactor building clean out.  This includes decommissioning, dismantlement and removal of building systems....

2022 – 2025

Planned activities include the decommissioning, dismantlement and removal of the purification building, service building, and resin storage tanks and vault....

2021 – 2025

Phase three is the next planned decommissioning phase for the facility. Planned activities include the decommissioning and removal of non-nuclear...

1987 – 2020

Phase 2 of decommissioning (1987 - 2020), known as "storage with surveillance" begins. In this stage, with fuel and coolant...

1984 – 1987

Operations cease and the facility is shut down.  In the first phase of decommissioning (1984 - 1987) fuel is removed...

1967 – 1984

Provides clean, reliable electricity to the grid, and valuable operating experience, helping to advance reactor development in Canada and internationally...